Meaders Lane Infrastructure Improvement Project
Posted on: April 20, 2023 - 10:19am

Phase I: SCOPE OF PROJECT WORK
Roadway, Sidewalk, & Drainage Improvements
- Meaders Lane (From Gove Lane to end of the road)
Water Main Improvements
- Meaders Lane
- Meaders Lane Ext.
- Gove Lane
- Short Lane
- Sandy Lane
Estimated Completion Date: May 20, 2023 +/-
PROJECT STATUS AS OF APRIL 20, 2023
Meaders Lane (From Gove Lane to end of Road)
WORK COMPLETED | WORK REMAINING |
- Drainage System Installed | - Install Granite Curbing |
- Water Main Installed and Tested | - Install Cement Concrete Sidewalk |
- Individual Water Services Installed | - Driveway Repair (south side) |
- Landscape Repair | |
- Reset Mailboxes |
Remaining Portion of Meaders Lane and Meaders Lane Ext.
WORK COMPLETED | WORK REMAINING |
- Water Mains Installed | - Water Main Connection at Beach Road |
- Test Meaders Lane Ext. Water Main | |
- Install Individual Water Services | |
- Pave Trenches | |
- Landscape Repair |
Gove Lane, Short Lane, Sandy Lane
WORK COMPLETED | WORK REMAINING |
- Water Mains Installed and Tested | - Install Individual Water Services |
- Gove Lane Individual Water Services Installed | - Pave Trenches |
- Landscape Repair |
NOTE: Upon completion of water main services, temporary water mains, and services will be removed.