Meaders Lane Infrastructure Improvement Project

Engineer

Phase I: SCOPE OF PROJECT WORK

 
Roadway, Sidewalk, & Drainage Improvements
  • Meaders Lane (From Gove Lane to end of the road)
Water Main Improvements
  • Meaders Lane
  • Meaders Lane Ext.
  • Gove Lane
  • Short Lane
  • Sandy Lane
Estimated Completion Date: May 20, 2023 +/-
 

PROJECT STATUS AS OF APRIL 20, 2023

 
    Meaders Lane (From Gove Lane to end of Road)    
WORK COMPLETED
WORK REMAINING
- Drainage System Installed
- Install Granite Curbing
- Water Main Installed and Tested
- Install Cement Concrete Sidewalk
- Individual Water Services Installed
- Driveway Repair (south side)
 
- Landscape Repair
 
- Reset Mailboxes
 
  Remaining Portion of Meaders Lane and Meaders Lane Ext.
WORK COMPLETED
WORK REMAINING
- Water Mains Installed
- Water Main Connection at Beach Road
 
- Test Meaders Lane Ext. Water Main
 
- Install Individual Water Services
 
- Pave Trenches
 
- Landscape Repair
 
  Gove Lane, Short Lane, Sandy Lane
WORK COMPLETED
WORK REMAINING
- Water Mains Installed and Tested
- Install Individual Water Services
- Gove Lane Individual Water Services Installed
- Pave Trenches
 
- Landscape Repair
 
NOTE: Upon completion of water main services, temporary water mains, and services will be removed.