Paving for Jak-Len Drive, Bayberry Lane, Main Street, and Toll Road will be conducted during the following schedule. Please keep in mind that for this project, vehicle access will be restricted to one side of the street. When that side is completed, Police details will change the traffic pattern to the other side of the street. Please plan accordingly. If you have any questions, please call Public Works at 978-462-7611.

Thursday, November 15th, 7 AM - Jak-Len Drive

A base course of asphalt will be installed. If you will need to get your car out, you should go to Toll Road, take a left, and park it along the road for the day. Please note that Toll Road will be getting the top course of asphalt on the 11/15 as well. Do not turn right onto Toll Road that day.

Monday, November 14th, 7 AM - Bayberry Lane

A top course of asphalt will be installed. For this activity, vehicle access will restricted. The paving will begin at the end of the street and move towards Toll Road. If you will need to get your car out, you should go to Toll Road, take a right, and park it along the road for the day. Please note that Toll Road will be getting the top course of asphalt on the 11/15. Do not turn left onto Toll Road that day.

Monday, November 14th & Tuesday, November 15th, 7 AM - Main Street and Toll Road

A top course of asphalt will be put down during these two days. Traffic will be pushed to one side of the road during this work and there will be a continuous flow of one-lane traffic.