Infrastructure Projects Phase 1

-A A +A

Lincoln Avenue Neighborhood Schedule

Phase 1

Start Date April 7, 2014

  • Installation of Erosion Control Measures
  • Temporary Bypass Piping
  • Sample Bypass
  • Installation of Temporary Bypass Piping
  • Sample Bypass
  • Pre-Excavation for Connections on Beach Road
  • Complete tie in on Beach Road
  • Saw Cut Trench
  • Unload Pipe
  • Pipe Installation
  • Pressure Test
  • Sample Pipe
  • Service Installation
  • Temporary Paving