Town Seal of Salisbury - 1638

 

Town of Salisbury, MA

Rabbit Road Sewer & Water Project

 



 

Home

Town Officials

Town Departments

Town Boards
Meeting Schedule

History

Feedback

Links

CONTACTS:

NORM VOLPONE-CLERK OF THE WORKS

volponen@wseinc.com

978-265-5035

 

DON LEVESQUE-DPW DIRECTOR

dlevesque@salisburyma.gov

978-463-0656

 

LISA PEARSON-PLANNING DIRECTOR

lpearson@salisburyma.gov

978-463-2266

CONSTRUCTION LOOK AHEAD:

Date:  Wednesday, October 29, 2008

 

Rabbit Road, North, East & South is completed; Main Lines & Services.

 

Work is progressing on Fanaras Drive North from the proposed pump station site.

 

 

Date:  Thursday, September 25, 2008

 

1)  Paving along Rabbit Road from Fanaras North to Mini-Storage should be completed at the end of this week.

 

2)  Finish grading on Fanaras & placement of binder coarse from # 5 to Rabbit Road should be completed

     next week.

 

3)  Installation of Main line on Rabbit Road from Fanaras North will continue for next several weeks.

 

 

Date:  Thursday, August 28, 2008

 

The Town is advancing with construction of sewer & water main service along Rabbit Rd & Fanaras Dr. 

 

The following work has been completed:

 

Gravity & force main sewer installation, as well as water main replacement, is completed on Old Elm Street, and nearly complete on that portion of Rabbit Road from the Old Elm Street intersection to the southerly Fanaras Drive intersection.  The exception to this is a number of Rabbit Road sewer service connections that must still be installed.  Gravity & force main sewer installation is also complete on approx. 600 Ft of Fanaras Drive, from the southerly Rabbit Rd intersection to the proposed pump station.  This work has been accomplished under an Order of Conditions granted from the Salisbury Conservation Commission on June 10, 2008 and the contractor has moved forward to mobilize & perform work on Fanaras Dr. 

 

Date:  Tuesday, August 12, 2008

 

The 6" Force Main & 8" Gravity Main on Rabbit Road from Fanaras Drive South 4,000 Feet:

Both Mains should be completed by the end of this week.

 

Albanese will begin next week paving the Main Line trench, weather permitting.  3-4 days of dry weather is needed prior to paving for the area to dry out.

Date:  Friday, July 25, 2008

Rabbit Road is now open to all traffic.

Date: Tuesday, July 22, 2008

Baker Road will be closed at the intersection of Rabbit Road on Wednesday (7/23), Thursday (7/24) and Friday (7/25) from 7am-5pm.  Local traffic only.  Residents are requested to use True Road, Bartlett Street or Cushing Street.

Date:  Tuesday, July 15, 2008

Approximately 1,000 feet of sewer main has been installed (includes portion of Fanaras Drive).  Currently prepping & paving existing gravel trenches.  The project remains on schedule & no issues reported to date.

 

Date:  Wednesday, June 18, 2008

 

We are in the process of installing Water Services as well as Sewer Services on the Rabbit Road Water & Sewer Main Lines.  This work will continue through the end of this week.

Equipment has been sent to Fanaras Drive & work in that area should commence the beginning of next week

As of 1:00pm on June 5, 2008:  The water is now back on at Rabbit Road (between Baker & Old Elm)...ahead of schedule! 

 

A Water Shutdown will occur Thursday, June 5th, between the hours of 7am & 4pm.  (We anticipate the water being off for the entire period.)  There are two (2) hydrants involved.  The areas that will be impacted are Rabbit Road, between Baker Avenue & Old Elm Street.  Pennichuck has notified water customers in this area.

Date:  Wednesday, May 29, 2008

All Water Improvements & Sewer Extension have been completed for the Old Elm Street section of this project.

Old Elm Street is now paved & "looks great!"

 

Date:  Friday, May 23, 2008

  

1) All water services are completed & tested.

2) The new 12" Ductile Water Main is activated.

3) Three (3) new Sewer Services remain to be installed at the end of Old Elm Street.  (Scheduled for next week)

4) Pulverizing & Re-Claiming of the road is being performed today.

5) Grading of the roadway to start beginning of next week.

6) Asphalt is scheduled to be in place next week.  

7) All hydrants on Old Elm Street have been changed over to the new 12" ductile iron water main & are activated.  They now have better Flows on Old Elm Street.  (The Fire Dept. has been notified.)

 

Date:  Monday, May 19, 2008

 

1) Tie-In Rabbit Rd & Old Elm St Water Mains.

2) All water services & Main have been installed.  (They will be chlorinated & tested in the near future.)

3) Sewer services & sewer main to be completed on Old Elm Street this week.

 

Date:  Tuesday, May 13, 2008

 

A new 12" water line is installed with appropriate gates & will be ready for use in approximately two weeks.

New sewer system is being installed with appropriate connections.  We have approx. 1,800' completed as of this week.

Excavation on Rabbit Road is scheduled for next Monday, May 19th. 

 

Date:  Monday, May 5, 2008

 

To date, 1500' of sewer has been installed, 700' of water main completed, and 7 house connections.   

This week's schedule includes finishing water main installation and extension of water main on Elm Street.  Major water shut downs are scheduled for this Wednesday, May 7th, between Robert's Electric & the intersection of Old Elm Street.  Tony from Pennichuck Water is going door-to-door to notify residents of the shut-down.   He will leave written notice (yellow tag) on the outside door.  Water is expected to remain off for approximately 4-6 hours on May 7th. 

Map of Project

FREQUENTLY ASKED QUESTIONS:

Q:  What is the scope of the project?

           A:  Sewer-Installation of 9,000 linear feet of sewer main/laterals

                 Water-Replacement and upgrade of water main/services on Elm St, Old Elm St, Rabbit Rd and Fanaras Dr

Q:  How long should the project take?

           A:  Approximately two years 

Q:  Who is overseeing the project?

           A:  The Town of Salisbury and Weston and Sampson Engineering are overseeing the project and are onsite everyday. 

Q: Will there be road closures?

           A:  Minimal road closures are anticipated.

Q: Who is the contractor? 

           A:  Albanese Brothers, Inc. of Dracut, MA

Q:  How invasive will this be to our property?

           A:  This project should be minimally invasive to your property.  When your water line is connected to the new water main, we  will be working in the area of your water shut off box, which is located at the point where your property line meets the Town’s property line (near the public roadway).  The sewer portion should not affect you at all during the installation.  Once the project is complete, you will be allowed to tie in to the new sewer line. 

Q:  Will we be inconvenienced driving in/out of driveways or on the roadway?

           A:  On occasions, you may be inconvenienced, but, it is our plan to keep all such problems to a minimum.  Norm Volpone (see contact information above),the engineer representing the Town, will be on site during the construction process to address any such issues. 

Q:  Will we be required to tie into the sewer line if our septic system is fairly new?

           A:  No, you will not be required to tie into the municipal sewer unless you have a failed septic system.

Q:  If we choose to tie in will it benefit us to do so sooner rather than later?

           A:  When you connect to the municipal sewer system, you will be required to pay a sewer access fee of approximately $3,000.  The fee usually increases 3% to 4% each year.  Everyone will be assessed a betterment at the same time. You will be responsible to pay that whether or not you choose to tie in immediately upon completion of the project or if you wait until your septic system fails.

Q:  If my septic system is in failure, can I tie-in when the sewer line passes my property?

           A:  No, tie-in is only allowed after the project is complete to assure that the project is done properly.

Q:  If I want to sell my property before the project is complete and my septic system is in failure, what do I do?

           A:  Contact the Board of Health at 978-462-3430 and they will advise you on the proper steps.

Q:  If I currently have a sewer waiver from the Board of Health because I am in failure, am I still responsible for renewing that annually?

           A:  Yes

Q:  Will we be compensated if any damages occur to our property during this project?

           A:  Yes.

Q:  Why is the Assessor contacting me about this project?

           A:  The Assessor will be contacting property owners (mostly commercial and industrial properties) to complete an inspection.  This is necessary in order to properly determine the EQRs and subsequent betterments.  Several inspections have already been scheduled as a result of the April 10 meeting.  Your cooperation will lead to an accurate assessment of betterment fees.

Article in The Newburyport Daily News Article-2/27/08:

            http://www.newburyportnews.com/punews/local_story_058072637.html

 

 

 

 

 

 

 

 

 

 

 

 

| home | officials | departments | boards | history| feedback | links |